Answer:
Project Beta IRR project's cost of equity
W .63 9.4% = 5.1% + (0.63 x 7%) = 9.51%
X .76 10.5% = 5.1% + (0.76 x 7%) = 10.42%
Y 1.29 14.0% = 5.1% + (1.29 x 7%) = 14.13%
Z 1.40 17.1% = 5.1% + (1.40 x 7%) = 14.9%
the company's cost of capital = 12%
a. Which projects have a higher/lower expected return than the firm’s 12.1 percent cost
of capital?
- higher expected return ⇒ projects Y and Z
- lower expected return ⇒ projects W and X
b. Which projects should be accepted?
- accepted ⇒ projects X and Z (their IRR is higher than their Re)
- rejected ⇒ projects W and Y (their IRR is lower than their Re)
c. Which projects will be incorrectly accepted/rejected or correctly accepted/rejected if the firm's overall cost of capital were used as a hurdle rate?
- if the company uses its cost of capital, then it would incorrectly reject project W and incorrectly accept project Y