Answer:
the order point is 19
Step-by-step explanation:
The computation of the order point is shown below:
Order point is
= Demand during lead time + safety stock
= 11 + 8
= 19
hence, the order point is 19
We simply applied the above formula so that the correct value could come
And, the same is to be considered
And ignored the demand during review cycle as it is relevant for the calculation of the order point