109k views
3 votes
Suppose the weekly amount of money spent on maintenance and repairs by a company is NOT approximately normally distributed. However, its mean and standard deviation are known to be $400 and $20, respectively. If $450 is budgeted for next week, what can you say about the probability that the actual costs will exceed the budgeted amount

1 Answer

3 votes

Answer:

Probability = 0.00621

Explanation:

We are given;

Population mean; μ = 400

Population standard deviation; σ = 20

Raw score; x¯ = 450

the probability that the actual costs will exceed the budgeted amount will be the p-value.

Thus, let's first find the z-score after which we will find the p-value.

z = (x¯ - μ)/σ

z = (450 - 400)/20

z = 50/20

z = 2.5

From online p-value from z-score calculator attached, using z = 2.5; one tailed hypothesis; significance level of 0.05, we have;

P-value = 0.00621

Suppose the weekly amount of money spent on maintenance and repairs by a company is-example-1
User Alan Carwile
by
8.1k points

No related questions found

Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories