A master production schedule quantity of 300 units will arrive in week 6. Weekly demand over weeks 3 through 10 is forecasted at 50 units. At present, orders have been booked in various quantities in weeks 1, 2, 3 and 4. What is the available to promise for week 6

1 Answer

3 votes

Answer: 300 units.

Step-by-step explanation:

Given data:

Scheduled quantity to arrive in 6 weeks.

= 300

Booked order = week (1,2,3,4).

Because the order for week 1 through 4 has been booked, and a scheduled quantity of 300 unit is expected to arrive by the 6th week. The available promise for week 6 would be 300 units.

Because that’s the expected unit for week 6.