The question is:
Define the event C : (project completed on time) in terms of E, F and S. Compute the probability P(C) operations will not be on time in terms of E, F and S.
Solution:
The events are:
E = excavation completed on time; P [E] = 0.8
F = foundation completed on time; P [F] = 0.7
S = superstructure completed on time; P [S] = 0.9
The event C denotes the completion of the project on time.
Compute the probability of event C as follows:
P (C) = P (E ∩ F ∩ S)
= P (E) × P (F) × P (S)
= 0.8 × 0.7 × 0.9
= 0.504
Thus, the probability of the completion of the project on time is 0.504.