45.4k views
1 vote
In a building construction project, the on-time completion of the building requires the successive completion of a series of activities. Define E = excavation completed on time; and P[E] = 0.8 F = foundation completed on time; and P[F] = 0.7 S = superstructure completed on time; and P[S] = 0.9 Assume statistical independence among these events.

User Aminouvic
by
7.9k points

1 Answer

4 votes

Answer:

The probability of the completion of the project on time is 0.504.

Explanation:

The question is:

Define the event C : (project completed on time) in terms of E, F and S. Compute the probability P(C) operations will not be on time in terms of E, F and S.

Solution:

The events are:

E = excavation completed on time; P [E] = 0.8

F = foundation completed on time; P [F] = 0.7

S = superstructure completed on time; P [S] = 0.9

The event C denotes the completion of the project on time.

Compute the probability of event C as follows:

P (C) = P (E ∩ F ∩ S)

= P (E) × P (F) × P (S)

= 0.8 × 0.7 × 0.9

= 0.504

Thus, the probability of the completion of the project on time is 0.504.

User Macleojw
by
8.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.