217k views
5 votes
Grady is excavating the foundation of a house. If the hole will be

40 feet long, 24 feet wide, and 4 feet deep, how many cubic feet
of dirt must be removed from the site?

1 Answer

4 votes

Answer:

3,840 cubic feet

Explanation:

V=LWH

V= 40X24X4

V=3,840 cubic feet

User Bill Christenson
by
3.8k points