52.6k views
4 votes
Lambda Computer Products competed for and won a contract to produce two prototype units of a new type of computer that is based on laser optics rather than on electronic binary bits. The first unit produced by Lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies. The second unit took 4,250 hours and used $237,500 worth of materials, equipment usage, and supplies. Labor is $20 per hour. Use Exhibit 6.5. a. Lambda was asked to present a bid for 10 additional units as soon as the second unit was completed. Production would start immediately. What would this bid be

User Aweary
by
4.1k points

1 Answer

3 votes

Answer:

$2,731,672.50

Step-by-step explanation:

first unit produced by lambda took 5,000 hours to produce and required $250,000 worth of material, equipment usage, and supplies

the second unit took 4,250 hours and used $238,500 worth of materials, equipment usage, and supplies

learning rate = time needed to produce second unit / time needed to produce first unit = 4,250 hours / 5,000 hours = 85%

materials and equipment usage rate = $237,500 / $250,000 = 95%

using the attached table of cumulative values, we can determine the cumulative improvement factors needed to solve this question:

Lambda's accumulated cost for producing 10 more computers

  • work hours = 4,250 x 7.116 (85% and 10 units) x $20 per hour = $604,860
  • materials and equipment = $238,500 x 8.955 (95% and 10 units) = $2,126,812.50
  • total = $604,860 + $2,126,812.50 = $2,731,672.50
Lambda Computer Products competed for and won a contract to produce two prototype-example-1
User George Dimitriadis
by
4.4k points