Answer:
$10 per unit
Step-by-step explanation:
The average total cost (AC) is the estimated per-unit cost in a given output. The formula for calculating the average cost
=(Total fixed costs + total variable costs) / number of units produced = average total cost.
Adding Total fixed cost to total variable cost equal to Total cost (TC)
For this business, the average total costs
=$45,000 + $32,000 /7,700
=$77,000/7700
=$10
AC= $10 per unit