Answer:
$350
Step-by-step explanation:
We can calculate the expected NPV by calculating the present value of future cash flows first and then deduct these cash flows from the initial investment.
DATA
Inital Investment = $ 20,000
cost of capital = 13%
Calculation
Expected Cash flow for year 1 = $ 26,000 x 40% = 10,400
Expected Cash flow for year 2 = $3,000 * 0.6 = 1800
Expected cash flow = 12,200
Present value of future cash flows = $12,200/1.13 + $12,200/(1.13)^2
Present value of future cash flows = $10,796 + $9,554
Present value of future cash flows = $20,350
Expected NPV of the project = Present value of future cash flows - Initial Investment
Expected NPV of the project = $20,350 - $20,000 = $350
Requirement B
Present value of future cashflows = 20350
Present value of renewal in year2 = 20,000/(1.13)^2 = $15,673
Inital = $20,000
NPV = 20,350 - 20,000 - 15,673
NPV = -15,323