When building a house, the number of days required to build is inversely proportional to with the number of workers. One house was built in 110 days by 8 workers. How many days would it take to build a similar house with 44 workers?

User Kyle Simek
by
8.6k points

1 Answer

1 vote

Answer:

605

Explanation:

1. 110:8

2. 110÷8=13.75

3. 13.75×44=605