Answer: 125%
Step-by-step explanation:
Manufacturing overhead = Predetermined overhead rate * Direct labor
Manufacturing Overhead
= Work in process balance - Direct labor - Direct materials
= 3,960 - 640 - 440 - 540 - 740
= $1,600
The rationale behind the above is that that the Work in process account is made up of Direct labor, material and overhead. The Overhead would therefore be the balance less the Direct material and labor.
Direct Labor = 540 + 740
= $1,280
Manufacturing overhead = Predetermined overhead rate * Direct labor
1,600 = Predetermined overhead rate * 1,280
Predetermined overhead rate = 1,600/1,280
= 1.25
= 125%