Answer:
Complete the following statements: THEORETICAL CAPACITY would result in the largest production volume variance; NONE OF THE CAPACITY CHOICES would result in a favorable production volume variance.
a. theoretical capacity; none of the capacity choices
Step-by-step explanation:
production volume variance = (actual unit quantity manufactured - budgeted unit quantity manufactured) x budgeted cost per unit
(actual production - theoretical capacity) x budgeted cost per unit = (250,000 - 275,000) x budgeted cost = 25,000 x budgeted cost
None of the capacity choices would result in a favorable variance because actual production was lower than all of them.
actual production 250,000 < theoretical 275,000
actual production 250,000 < practical 265,000
actual production 250,000 < normal 260,000