On January 1, 2016, Dreamworld Co. began construction of a new warehouse. The building was finished and ready for use on September 30, 2017. Expenditures on the project were as follows: January 1, 2016 $319,000 September 1, 2016 $468,000 December 31, 2016 $468,000 March 31, 2017 $468,000 September 30, 2017 $319,000 Dreamworld had $5,600,000 in 12% bonds outstanding through both years. Dreamworld's capitalized interest in 2016 was:

1 Answer

0 votes

Answer:

$638,000.

$319,000.

$475,000.

$554,750.

My respond is 638,000