Answer:
$5,350,000
Step-by-step explanation:
The computation of the overhead applied to supreme using activity based costing is shown below:
= Machine hours × machine hour rate + number of parts × cost per part
= 30,000 × ($5,000,000 ÷ (10,000 + 30,000)) + 160,000 × ($2,500,000 ÷ (90,000 + 160,000))
= 30,000 × $125 + 160,000 × $10
= $3,750,000 + $1,600,000
= $5,350,000
Hence, the overhead applied to supreme is $5,350,000