Question:
standard total cost Actual total cost
Direct material
Standard 2000 pints $3.50/pint $7,000
Actual 2,500 pints $5.00/pint $12,000
Answer:
Materials quantity variance= $1,750 unfavorable
Step-by-step explanation:
Material quantity variance occurs when the actual quantity used to achieved a given level of output is more or less than the standard quantity.
It is determined by the difference between the actual and standard quantity of material for the actual level of output multiplied by the the standard price
pints
Standard quantity allowed 2,000
Actual quantity used 2,500
Quantity variance 500 unfavorable
Standard price $3.50
Materials quantity variance 1,750 unfavorable
Materials quantity variance= $1,750 unfavorable