Answer:
$195,751
Step-by-step explanation:
Calculation for the project's expected operating cash flow
The first step will be to find the EBIT
using this formula
EBIT =(Earnings before interest, taxes, depreciation, and amortization -Depreciation expense)
Let plug in the formula
EBIT= 283,104 - 53,228
EBIT= 229,876
Second step is to find the NOPAT using this formula
NOPAT = EBIT(1- tax rate)
NOPAT= 229,876(1 - 0.38)
NOPAT= 142,523
Last step is to calculate for Expected Operating Cash flow
Using this formula
Operating cash flow = NOPAT + Depreciation expenses
Let plug in the formula
Operating cash flow = 142,523 + 53,228
Operating cash flow = $195,751
Therefore the project's expected operating cash flow will be $195,751