In its third year, a project is expected to generate earnings before interest, taxes, depreciation, and amortization of $283,104 and its depreciation expense is expected to be $53,228. If the company’s tax rate is 38%, what is the project’s expected operating cash flow?

1 Answer

2 votes

Answer:

$195,751

Step-by-step explanation:

Calculation for the project's expected operating cash flow

The first step will be to find the EBIT

using this formula

EBIT =(Earnings before interest, taxes, depreciation, and amortization -Depreciation expense)

Let plug in the formula

EBIT= 283,104 - 53,228

EBIT= 229,876

Second step is to find the NOPAT using this formula

NOPAT = EBIT(1- tax rate)

NOPAT= 229,876(1 - 0.38)

NOPAT= 142,523

Last step is to calculate for Expected Operating Cash flow

Using this formula

Operating cash flow = NOPAT + Depreciation expenses

Let plug in the formula

Operating cash flow = 142,523 + 53,228

Operating cash flow = $195,751

Therefore the project's expected operating cash flow will be $195,751