The amount of safety time needed to protect a particular path in a project is less than the sum of the safety times required to protect the individual activities making up the path.

a. True
b. False

1 Answer

4 votes

Answer:

a. True

Step-by-step explanation:

For computing the amount of safety time required for protecting a specific path we need to subtract the total of safety time in order to protect the individual activities who are making the path so that the path should be secure, safe and protected

Hence, the given statement is true

Therefore the correct option is a. True