The length of time a full length movie runs from opening to credits is normally distributed with a mean of 1.9 hours and standard deviation of 0.3 hours. Calculate the following: A random movie is between 1.8 and 2.0 hours. A movie is longer than 2.3 hours. The length of movie that is shorter than 94% of the movies

User Deon
by
7.3k points

1 Answer

1 vote

Answer:

  1. 0.26
  2. 0.91
  3. 1.43

Explanation:

given data

mean = 1.9 hours

standard deviation = 0.3 hours

solution

we get here first random movie between 1.8 and 2.0 hours

so here

P(1.8 < z < 2 )

z = (1.8 - 1.9) ÷ 0.3

z = -0.33

and

z = (2.0 - 1.9) ÷ 0.3

z = 0.33

z = 0.6293

so

P(-0.333 < z < 0.333 )

= 0.26

so random movie is between 1.8 and 2.0 hours long is 0.26

and

A movie is longer than 2.3 hours.

P(x > 2.3)

P(
(x-\mu )/(\sigma) >
(2.3-\mu )/(\sigma) )

P (z >
(2.3-1.9 )/(0.3) )

P (z > 1.333 )

= 0.091

so chance a movie is longer than 2.3 hours is 0.091

and

length of movie that is shorter than 94% of the movies is

P(x > a ) = 0.94

P(x < a ) = 0.06

so

P(
(x-\mu )/(\sigma ) <
(a-\mu )/(\sigma ) )


(a-1.9 )/(0.3 ) = -1.55

a = 1.43

so length of the movie that is shorter than 94% of the movies about 1.4 hours.