Answer:
$13,000
Step-by-step explanation:
The total budgeted cost is $15,000
The cumulative actual cost is $10,000
The cumulative earned value is $12,000
Therefore, the forecasted cost at completion can be calculated as follows
= Cumulative actual cost + ( Budgeted cost-Cumulative earned value)
= $10,000 + ($15,000-$12,000)
= $10,000 + $3,000
= $13,000
Hence the forecasted cost at completion is $13,000