Answer:
Total budget overhead cost = $15,000
Step-by-step explanation:
Given:
Each watch take time = 5 hour
Variable cost = $4 per hour
Fixed overhead cost = $5,000 per month
Total number of watches = 500
Find:
budget in overhead costs
Computation:
Total variable cost = Total number of watches × Each watch take time × Variable cost
Total variable cost = 500 × 5 × $4
Total variable cost = $10,000
Total budget overhead cost = Total variable cost + Fixed overhead cost
Total budget overhead cost = $10,000 + $5,000
Total budget overhead cost = $15,000