Parker & Stone, Inc., is looking at setting up a new manufacturing plant in South Park to produce garden tools. The company bought some land 10 years ago for $5 million in anticipation of using it as a warehouse and distribution site, but the company has since decided to rent these facilities from a competitor instead. If the land were sold today, the company would net $9.6 million. The company wants to build its new manufacturing plant on this land; the plant will cost $15.2 million to build, and the site requires $960,000 worth of grading before it is suitable for construction.

What is the proper cash flow amount to use as the initial investment in fixed assets when evaluating this project?
Cash Flow amount $ _____

1 Answer

6 votes

Answer:

$25,760,000

Step-by-step explanation:

The net amount of decrease and increase of cash a business or individual owns.

To find the proper cash flow amount used as the initial investment in fixed assets, use the following:

Calculation of initial investment outflow = cost of land + cost of plant + grading cost

= $9,600,000 + 15,200,000, + $960,000

= $25,760,000

Calculation of initial investment outflow = $25,760,000

Therefore the initial investment outflow is $25,760,000