Please Assist With This Equation

*Please Show Work*​

Please Assist With This Equation *Please Show Work*​-example-1

1 Answer

3 votes

Answer:

240 hours

Explanation:

One person hour is a unit indicating the rate at which one person is working on the project .

The company estimates that it will take 2880 person- hours to complete the job

So let's determine how many hours it will take 12 workers to complete same job

The rate = 2880 person/hour

12 persons or workers =( 2880 person/hour)/12 persons

12 persons or workers = 2880/12

12 persons or workers=240 hours

It will take 12 workers 240 person hour to finish the project.