Answer:
The required return for the new project is 6.87%
Step-by-step explanation:
In order to calculate the required return for the new project we would have to calculate the Weighted Average Cost of Capital (WACC) adjusted by risk adjustment factor .
The Weighted Average Cost of Capital (WACC) = [After Tax Cost of Debt x Weight of Debt] + [Cost of equity x Weight of Equity]
After -tax Cost of Debt = 3.40%
Cost of Equity = 10.80%
Weight of Debt = 0.39
Weight of Equity = 0.69
Therefore, the Weighted Average Cost of Capital (WACC) = [After Tax Cost of Debt x Weight of Debt] + [Cost of equity x Weight of Equity]
= [3.40% x 0.39] + [10.80% x 0.69]
= 1.32% + 7.45%
= 8.77%
The required return for the new project = Weighted Average Cost of Capital – Risk Adjustment Factor
= 8.77% - 1.90%
= 6.87%
The required return for the new project is 6.87%