Answer:
$72
Explanation:
For computation of overhead is allocated to the job first we need to find out the each department of manufacturing overhead allocated which is shown below:-
Manufacturing overhead allocated for Machining = Machine hours × Departmental overhead rate
= 4 × $15
= $60
Manufacturing overhead allocated for Sanding = Machine hours × Departmental overhead rate
= 1 × $6
= $6
Manufacturing overhead allocated for Painting = Machine hours × Departmental overhead rate
= 2 × $3
= $6
So, Total overhead is allocated to the job = Manufacturing overhead allocated for Machining + Manufacturing overhead allocated for Sanding + Manufacturing overhead allocated for Painting
= $60 + $6 + $6
= $72