Answer:
$9,300 unfavorable
Step-by-step explanation:
The computation of the direct material cost variance is shown below:
Direct material cost variance = standard cost - actual cost
where,
Actual cost is $99,300
And, the standard cost is
= 7,500 pounds of direct material × $12 per pound
= $90,000
So, the direct material cost variance is
= $90,000 - $99,300
= $9,300 unfavorable
Basically we applied the above formula to find out the direct material cost variance