Answer:
c) 5 days, 7 workers
Step-by-step explanation:
The longest task is Task-1 which takes 5 days.
All the tasks are parallel. So, the length of the project should be 5 days. The resources employed are just the total of all the tasks i.e. 2+2+1+1+1 = 7.
5 days, 7 workers