Given this project and the requirement that the number of resources working on a task cannot be less than the number assigned to the task, answer the following question. What is the least amount of time that the project can be completed and how many resources are required to complete the work?

Task 1 2 workers needed 5 days
Task 2 2 workers needed 3 days Start Project
Task 3 1 worker needed 2 days Finish Project
Task 4 1 worker needed 4 days
Task 5 1 worker needed 2 days
a) 16 days, 7 workers
b) 7 days, 5 workers
c) 5 days, 7 workers
d) 8 days, 3 workers

User Cwadding
by
6.7k points

1 Answer

3 votes

Answer:

c) 5 days, 7 workers

Step-by-step explanation:

The longest task is Task-1 which takes 5 days.

All the tasks are parallel. So, the length of the project should be 5 days. The resources employed are just the total of all the tasks i.e. 2+2+1+1+1 = 7.

5 days, 7 workers