Answer:
a) Identify which project should the company accept based on NPV method.
- Project 2 has a higher NPV = $98,960
b) Identify which project should the company accept based on simple pay back method if the payback criteria is maximum 2 years.
- Project 2 has a shorter payback period = 2 years and 5 months
c) Which project Giant Machinery should choose if two methods are in conflict.
- If two projects are in conflict, then you must choose the project based on their NPV.
Step-by-step explanation:
Project 1 Project 2
Cost $175, 000 $185 ,000
Future Cash Flows
Year 1 $76,000 $83,000
Year 2 $67,000 $65,000
Year 3 $55,000 $87,000
Year 4 $78,000 $69,000
Year 5 $65,000 $57,000
NPV:
Project 1 = -175000 + 76000/1.09 + 67000/1.09² + 55000/1.09³ + 78000/1.09⁴ + 65000/1.09⁵ = $91,090
Project 2 = -185000 + 83000/1.09 + 65000/1.09² + 87000/1.09³ + 69000/1.09⁴ + 57000/1.09⁵ = $98,960
Payback:
Project 1 = -175000 - 76000 - 67000 = 32000 after 2 years, then 32000 / 55000 = 7 months
Project 2 = -185000 - 83000 - 65000 = 37000 after 2 years, then 37000 / 87000 = 5 months