g Job 397 was recently completed. The following data have been recorded on its job cost sheet: Direct materials $ 44,000 Direct labor-hours 630 DLHs Direct labor wage rate $ 12 per DLH Number of units completed 2,000 units The company applies manufacturing overhead on the basis of direct labor-hours. The predetermined overhead rate is $12 per direct labor-hour. Required: Compute the unit product cost that would appear on the job cost sheet for this job.

1 Answer

6 votes

Answer:

$29.56

Step-by-step explanation:

The computation of unit product cost is shown below:-

Unit product cost = (Direct material + Direct labor + Manufacturing overhead) ÷ Number of units completed

= ($44,000 + (63 × $12) + ($12 × 630)) ÷ 2,000

= ($44,000 + $7,560 + $7,560) ÷ 2,000

= $59,120 ÷ 2,000

= $29.56

Therefore for computing the unit product cost we simply applied the above formula.

User Dbanas
by
7.9k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.

9.4m questions

12.2m answers

Categories