Answer:
Total fixed costs= $7,059
Total variable cost= $7,488
Total cost= $14,547
Step-by-step explanation:
Giving the following information:
Total Labor Cost = -7,059 + ($1.92*Employee Hours)
Required:Assume that 3,900 employee hours are budgeted for the coming year.
The total fixed costs remain constant with production:
Total fixed costs= 7,059
Total variable cost= 1.92*3,900= 7,488
Total cost= $14,547