Answer:
Step-by-step explanation:
Average arrival rate, λ = 5 people in 15 minutes = 20 people in 60 minutes = 20 per hour
Average service rate, μ = 1 in 7 minutes = (60/7) per hour
The minimum number of servers required for a stable queuing system = λ / μ = 20 / (60/7) = 7/3 = 2.333
So, the minimum number of hosts that could be hired = 3 hosts