Answer:
Total cost per hours= $111.3
Step-by-step explanation:
Giving the following information:
The activity of 9,600 hours:
Total variable cost= $827,520
Total fixed costs= $248,490.
First, we need to calculate the unitary variable cost:
Unitary variable cost= 827,520/9,600= $86.2
Because the 9,900 units are between the relevant range, the total fixed costs remain the same. For the same reason, the unitary variable cost per hour remains the same. Only the total variable cost varies with production (in unitary terms is constant).
Unitary cost per hout= $86.2
Unitary fixed cost= 248,490/9,900= $25.1
Total cost per hours= $111.3