Answer:
13.5
Step-by-step explanation:
The calculation of Number of kanbans needed is shown below:-
Demand during lead time = Daily demand × Production lead time
= 150 × 3.00
= 450
Safety stock = Safety stock × Daily demand
= 1.50 × 150
= 225
Number of kanbans needed = (Demand during lead time + safety stock) ÷ Kanban size
= (450 + 225) ÷ 50
= 675 ÷ 50
= 13.5
So, for calculating the number of Kanbans needed we simply applied the above formula.