Answer:
$32,900 favorable
Step-by-step explanation:
The computation of the total flexible budget variable overhead cost variance is shown below:
= Total budgeted overhead cost - actual budgeted overhead cost
where,
Total budgeted overhead cost is
= $9.40 × 74,900 hours
= $704,060
And, the actual budgeted overhead cost is
= $8.40 × 79,900 hours
= $671,160
So, the total flexible budget variable overhead cost variance is
= $704,060 - $671,160
= $32,900 favorable
Since the standard cost is greater than the actual cost so it would have favorable variance