Answer:
The current earned dollar value of the work in place (completed) is $2,268. The right answer is b
Step-by-step explanation:
According to the given data we have the following:
total pipeline installed=60+70+50= 180 ft
total cost= $ 5,040
unite price of pipeline=$5,040/400=$12.6
Therefore, in order the current earned dollar value of the work in place completed we would have to use the following formula:
current earned value= pipeline installed*unit price of pipeline=
current earned value=180 *$12.6
current earned value=$2,268
The current earned dollar value of the work in place (completed) is $2,268