Answer:
$634,443
Step-by-step explanation:
The computation of total overhead applied to Product P4 under activity-based costing is shown below:-
Activity Expected Expected Activity
costs Activity Rate
a b c = a ÷ b
Labor related $145,000 6,000 DLHs 24.17 per DLHs
Production
orders $68,360 1,400 orders 48.83 Per orders
Order size $1,069,190 5,800 MHs 184.34 per MHs
Product P4
Activity driver Overhead
Incurred Assigned
d e = c × d
2,000 $48,340
300 $14,649
3,100 $571,454
Total overhead cost $634,443