A project can be completed by 5 workers in 24 days. How many workers are needed to finish the project in 15 days? The time

to complete a project is inversely proportional to number of people who are doing the project.
a 10
c. 6
b. 12
d. 8

User Tzomas
by
5.4k points

2 Answers

5 votes

Answer:

d.8

Explanation:

User Trevis
by
5.3k points
5 votes
Answer: 8

Step by step explanation: 5 times 24 equals 120, 120 divided by 15 equals 8 which is the answer!