183k views
0 votes
In class Assignment Setup of Production FacilityJobs Description Duration/ Weeks Predecessors1 Design production tooling 4 - 2 Prepare manufacturing drawings 6 - 3 Prepare production facility 10 - 4 Procure tooling 12 1 5 Procure production parts 10 2 6 Kit parts 2 3,4,5 7 Install tools 4 3,4 8 Testing 2 6,7 1. Draw the network diagram2. What is the critical path

1 Answer

5 votes

Answer:

See explaination

Step-by-step explanation:

Critical path method (CPM) is a step-by-step process by which critical and non-critical tasks are defined so that time-frame problems and process bottlenecks are prevented.

please see attachment for the step by step solution of the given problem.

In class Assignment Setup of Production FacilityJobs Description Duration/ Weeks Predecessors-example-1
In class Assignment Setup of Production FacilityJobs Description Duration/ Weeks Predecessors-example-2