Answer:
Total cash made is $285
Explanation:
The amount made from Land Development Services is the minimum billable amount in respect of 1 hour (actual was 20 mins,but the minimum bill is $95 per hour)
Besides,the TG& R's plat revision even though took 10 minutes to complete would still be charged the minimum bill of $95
Mechanical Creations bearing design would cost $95 as well when actual time spent was 40 minutes.
It would have been a different discussion entirely if these services were rendered to one single client.
The total revenue earned is computed thus:
Land Development Services $95
TG& R $95
Mechanical creations $95
Total cash made $285