Note: The given table is not clearly expressed, check the attached file for the complete question
Answer:
Cumulative project budget for September = $251382
Explanation:
The cumulative project for September in this time-phased budget is:
Sum of July budget + Sum of August budget + sum of September budget
Sum of July budget = 34721 + 11049 + 33718
Sum of July budget = $79,488
Sum of August budget = 33655 + 34474+7713
Sum of August budget = $75842
Sum of September budget = 34388 + 26759+ 34905
Sum of September budget = $96052
Cumulative project budget for September = 79,488 + 75832 + 96052
Cumulative project budget for September = $251382