What is the cumulative project budget for September in this time-phased budget? Activity July August September October November RFP 34,721 ​ ​ ​ ​ Analysis 11,049 33,655 34,388 ​ ​ Design 33,718 34,474 26,759 36,328 ​ Coding ​ 7,713 34,905 40,244 ​ Testing ​ ​ ​ 40,916 896 Training ​ ​ ​ 20,958 9,327 Roll-Out ​ ​ ​ ​ 8,186 $152,927 $251,382 $155,330 $96,052

1 Answer

7 votes

Note: The given table is not clearly expressed, check the attached file for the complete question

Answer:

Cumulative project budget for September = $251382

Explanation:

The cumulative project for September in this time-phased budget is:

Sum of July budget + Sum of August budget + sum of September budget

Sum of July budget = 34721 + 11049 + 33718

Sum of July budget = $79,488

Sum of August budget = 33655 + 34474+7713

Sum of August budget = $75842

Sum of September budget = 34388 + 26759+ 34905

Sum of September budget = $96052

Cumulative project budget for September = 79,488 + 75832 + 96052

Cumulative project budget for September = $251382

What is the cumulative project budget for September in this time-phased budget? Activity-example-1