MetaPro Systems is a​ start-up company that makes connectors for​ high-speed Internet connections. MetaPro has budgeted three hours of direct labor per​ connector, at a standard cost of $ 16 per hour. During​ August, technicians actually worked 195 hours completing 71 connectors. All 71 connectors actually produced were sold. MetaPro paid the technicians $ 16.80 per hour.What is MetaPro's direct labor efficiency variance for August?

User Calendarw
by
8.4k points

1 Answer

4 votes

Answer:

$304 Favorable

Step-by-step explanation:

The computation of direct labor efficiency variance is shown below:-

Direct Labor efficiency Variance = (Standard Labor Hour - Actual Labor Hour) × Standard Rate

= ((71 × 3) - 195)) × $16

= (214 - 195) × $16

= 19 × $16

= $304 Favorable

Therefore for computing the direct labor efficiency variance we simply applied the above formula.

User Troels
by
7.6k points
Welcome to QAmmunity.org, where you can ask questions and receive answers from other members of our community.