Answer:
Budgeted labour cost for the quarter = $60,480
Step-by-step explanation:
The labour budget shoes the estomated cost of labour hours required to achieve the production budget.
Direct labour budget:
Total production for the first quarter = 2,940 + 2,730 + 3,390 =8400 units
The labour budget in hours = Total production unit × standard hour
= 8400 × 0.6 hours
= 5040 hours
Total labour budget i ($) = Total labour hours × rate per hour
= 5040 × $12
= $60,480