Probability that this project is going to take more than 18 weeks = 0.99991
Explanation:
When independent distributions are combined, the combined mean and combined variance are given through the relation
Combined mean = Σ λᵢμᵢ
(summing all of the distributions in the manner that they are combined)
Combined variance = Σ λᵢ²σᵢ²
(summing all of the distributions in the manner that they are combined)
For this distribution, the total time the project will take = A + B
A ~ (15, 8)
B ~ (16, 4)
Combined mean = μ₁ + μ₂ = 15 + 16 = 31
Combined variance = 1²σ₁² + 1²σ₂² = 8 + 4 = 12
Combined Standard Deviation = √(12) = 3.464 weeks
So, with the right assumption that this combined distribution is a normal distribution
Probability that this project is going to take more than 18 weeks
P(x > 18)
We first normalize/standardize 18
The standardized score for any value is the value minus the mean then divided by the standard deviation.
z = (x - μ)/σ = (18 - 31)/3.464 = - 3.75
The required probability
P(x > 18) = P(z > -3.75)
We'll use data from the normal probability table for these probabilities
P(x > 18) = P(z > -3.75) = 1 - P(x ≤ -3.75)
= 1 - 0.00009 = 0.99991