Answer:
a) The standard time for the task is 1.456 minutes
b) 330 work units are produced
Step-by-step explanation:
According to the given data, the tn= 1.30 min for a repetitive task that produces one work unit per cycle and the company uses a PFD allowance factor of 12%, hence, in order to calculate the standard time for the task, we would have to use the following formula:
tstd=tn(1+Apfd)
tstd=1.30(1+0.12)
tstd=1.456 minutes.
To calculate the work units that are produced in an 8-hour shift at standard performance we calculate the following:
8×60 = 480 = 330 work units
1,456 1,456