Answer:
$146,200
Step-by-step explanation:
Synergy Inc
Flexible budget amount for July:
Direct materials cost [($86,000 / 10,000 hours) × 12,000 hours] $103,200
Power [($30,000 / 10,000 hours) × 12,000 hours] $36,000
Salary of plant supervisor
$7,000
Total flexible budget amount $146,200
Therefore the flexible budget amount for July is $146,200