Synergy Inc. produces plastic grocery bags. Synergy has developed a static budget for the month of July based on 10,000 direct labor hours. During the quarter, the actual activity was 12,000 direct labor hours. Data for July are summarized as follows: ​ ​ Static budget (10,000 hours) Actual costs (13,000 hours) Direct materials cost $ 86,000 $108,000 Power 30,000 37,000 Salary of plant supervisor 7,000 7,000 Total $123,000 $152,000 ​ Direct materials cost and power are variable costs. ​Salary of plant supervisor is a fixed cost. What is the flexible budget amount for July?

User IamMobile
by
7.3k points

1 Answer

4 votes

Answer:

$146,200

Step-by-step explanation:

Synergy Inc

Flexible budget amount for July:

Direct materials cost [($86,000 / 10,000 hours) × 12,000 hours] $103,200

Power [($30,000 / 10,000 hours) × 12,000 hours] $36,000

Salary of plant supervisor

$7,000

Total flexible budget amount $146,200

Therefore the flexible budget amount for July is $146,200