Which of the following schedules is (conflict) serializable? For each serializable schedule, determine the equivalent serial schedules.

a. r1(X); r3(X); w1(X); r2(X); w3(X);
b. r1(X); r3(X); w3(X); w1(X); r2(X);
c. r3(X); r2(X); w3(X); r1(X); w1(X);
d. r3(X); r2(X); r1(X); w3(X); w1(X);

User Pcambra
by
4.0k points

1 Answer

4 votes

Answer:

Step-by-step explanation:

to determine the equivalent serial schedules, find the solutions below

Which of the following schedules is (conflict) serializable? For each serializable-example-1