Answer:
28 hours
Explanation:
If Jerry alone can do the job in 21 hours, the amount of the job completed per hour is 1/21.
If Jerry and Kuba work together, they can do the job in 12 hours, so the amount of the job completed per hour is 1/12.
If the speed of Jerry is is J and the speed of Kuba is K, we have that:
J = 1/21
J + K = 1/12
1/21 + K = 1/12
4/84 + 84K/84 = 7/84
4 + 84K = 7
84K = 3
K = 3/84 = 1/28
If Kuba can do 1/28 of the job per hour, He can complete the job alone in 28 hours.